Jul.12.2000 50% Wind Tunnel Construction on Schedule




WIND TUNNEL CONSTRUCTION

Since starting construction on the 20th of May construction has been getting along smoothly. On the 10th of July we started construction of the tunnel itself. We plan to finish fixing the motor around mid-September, by which the whole of the tunnel should take shape. The construction schedule has been planned so that the construction of the tunnel itself would have a head start, before actual work starts on the main building from the 10th of August.