WIND TUNNEL CONSTRUCTION |
|
|
Since starting construction on the 20th of May construction has been
getting along smoothly. On the 10th of July we started construction
of the tunnel itself. We plan to finish fixing the motor around mid-September,
by which the whole of the tunnel should take shape. The construction
schedule has been planned so that the construction of the tunnel itself
would have a head start, before actual work starts on the main building
from the 10th of August.
|