▲ FROM
THE TOP
Constructions of the fan
Construction |
|
|
Construction of the fan, which is equivalent to the heart of the wind
tunnel, finished around the end of August. After running it on the
bench to confirm that the characteristics were up to our expectations,
it was shipped to the construction site on the 11th of September.
Unluckily this coincided with the heavy rain storms we had been having
those few days and we had to postpone the actual construction for
two days. However we were able to finish fixing the fan in place on
the 16th of September and the tunnel portion of the wind tunnel became
complete.
■Fan Bench Test
In this bench test we confirmed that the required margin actually
exists between the actual characteristics of the fan and the required
specifications, and that the carbon fibre vanes we developed improved
the overall characteristics by decreasing vibration, noise and improving
efficiency.
On top of the empirical evidence we were also found out that the actual
sound emmitted from the fan was more pleasing to the ear.
■Fan Assembly
he casing for the fan was divided into four parts for delivery so
the various construction tasks such as assembly of the lower case,
attaching the vanes, the fastening of the rotor to the motor were
all done on site. The inner diameter of the fan is 4.3m but this requires
1/100mm precision for the leveling and centering of the fan to the
tunnel.
Precise construction was carried out and the assembly was complete.
■Construction Resumed
The construction of the building itself was kept on hold until the
wind tunnel was fully complete. Work on the basic structure of the
building resumed at the beginning of September and was virtually complete
on the 18th.
In the second half of September we expect to finish putting up the
walls of the building, so this will be the last time we will be able
to view a see-through-cut-away of the building showing the wind tunnel
in all its glory. This is a precious photograph of this view.
|